M6 Planned Carriageway, Slip Road and Lane Closures

Below you can find details of planned closures on the M6 between junctions 2 and 19, for smart motorway works. If you have any queries and would like to speak to somebody about the planned closures, please contact SmartMotorways@highwaysengland.co.uk

Please note – due to safety and weather restrictions, the below closures are subject to change and cancellation. The list does not include any maintenance or emergency closures that may be required.

M6 Northbound

Date Duration Details Project Allow an extra Diversion Route
Monday 25 February 10pm to 6am Junction 17 to 18 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Tuesday 26 February 10pm to 6am Junction 17 to 18 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Wednesday 27 February 10pm to 6am Junction 17 to 18 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Thursday 28 February 9pm to 6am Junctions 13 to 14 lane closures M6 junctions 13 to 15 20 minutes  
Thursday 28 February 10pm to 6am Junction 16 to 19 lane closures M6 junctions 16 to 19 20 minutes  
Friday 1 March 10pm to 8am Junction 16 to 19 lane closures M6 junctions 16 to 19 20 minutes  
Saturday 2 March 10pm to 8am Junction 3 to 4 northbound full closure for gantry installation M6 junctions 2 to 4 15 minutes

 

 

 

25 minutes

M6 J2 – 4 Northbound

 

 

M6 J2-4 HGV diversion

Saturday 2 March 10pm to 8am Junction 16 to 19 lane closures, M6 junctions 16 to 19 20 minutes  
Sunday 3 March 10pm to 6am Junction 16 to 19 lane closures M6 junctions 16 to 19 20 minutes  

M6 Southbound

Date Duration Details Project Allow an extra Diversion Route
Monday 25 February 10pm to 6am M6 junction 3 southbound entry slip road closure for drainage works M6 junctions 2 to 4   M6 junction 3 SB entry slip diversion

 

Monday 25 February 9pm to 6am Junctions 13 to 12 for repairs to safety barrier. Area 9 works M6 junctions 13 to 15 20 minutes A449 Penkridge Junction 12 – 13 Diversion

 

Monday 25 February 10pm to 6am Junction 19 to 16 lane closures M6 junctions 16 to 19 20 minutes  
Tuesday 26 February 10pm to 6am Junction 3 southbound entry slip road closure for drainage works M6 junctions 2 to 4   M6 junction 3 SB entry slip diversion

 

Tuesday 26 February 9pm to 6am Junctions 13 to 12 for repairs to safety barrier. Area 9 works M6 junctions 13 to 15 20 minutes Via A449 Penkridge Junction 12 – 13 Diversion

 

Tuesday 26 February 10pm to 6am Junction 19 to 16 lane closures M6 junctions 16 to 19 20 minutes  
Wednesday 27 February 10pm to 6am Junction 3 southbound entry slip road closure for drainage works M6 junctions 2 to 4   M6 junction 3 SB entry slip diversion

 

Wednesday 27 February 10pm to 6am Junction 19 to 16 lane closures M6 junctions 16 to 19 20 minutes  
Thursday 28 February 10pm to 6am Junction 3 southbound entry slip road closure for drainage works M6 junctions 2 to 4   M6 junction 3 SB entry slip diversion

 

Thursday 28 February 10pm to 6am Junction 18 to 17 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Friday 1 March 10pm to 6am Junction 3 southbound entry slip road closure for drainage works M6 junctions 2 to 4   M6 junction 3 SB entry slip diversion

 

Friday 1 March 10pm to 8am Junction 18 to 17 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Saturday 2 March 10pm to 8am Junction 4 to 3 southbound full carriageway closure for gantry installation M6 junctions 2 to 4 15 minutes

 

25 minutes

M6 J4a – 2

 

M6 4a to 2 HGV diversion

 

Saturday 2 March 10pm to 8am Junction 18 to 17 full closure M6 junctions 16 to 19 45 minutes J17-J18 under 15ft 9

J17-J18 over 15ft 9

Sunday 3 March 10pm to 6am Junction 19 to 16 lane closures M6 junctions 16 to 19 20 minutes